Capital Projects Return $10.9 Million - 08 Sep 26
Richmond Hill · September 09, 2026
The live stream has begun.
Okay.
When when I get the signal, we'll call
the meeting to order.
>> Fireworks.
>> There. There it is. Okay. So, I call
this meeting to order. Uh budget
committee of the whole meeting. Um
purpose today is really to get an update
from our financial staff uh our capital
project financial status and our uh
forecast for 2026 year end. So um you
have the agenda before you. Can I get a
a motion to adopt the agenda? Thank you
councelor Silvitz. Any discussion there?
All in favor?
Any opposed? That carries unanimously.
Okay. Any members of the committee have
a disclosure of pecuniary interest?
I see none.
Okay, we don't have any delegations. We
go right to our scheduled business. And
the the first item 5.1 is a capital
project financial status report and a
presentation by GI Lee, our director of
financial services and treasur up to 15
minutes with this presentation.
Go ahead, Miss Lee.
Good afternoon, budget Dala and members
of the committee. We have two related
reports that are before the budget
committee today. The first one is the
2026 capital project financial status
report.
The second being the 2026 year and
operating forecasts. These reports are
provided to council annually detailing
forecasts for use of budgeted funds of
the operating programs as well as the
capital projects. The first report which
is the capital project financial status
report covers project closures, budget
and funding adjustments, time critical
in-ear additions as well the status of
open capital projects as of June 30th,
2026.
The purpose of this report is to give
committee a mid-year picture of where
our capital program stands, which
projects are complete and ready to
close, what surplus funding can be
returned, and what adjustments are
needed on active projects, and how the
overall open project portfolio is
tracking against the approved budget.
This slide highlights the net picture at
a glance.
Closing 186 projects in appendix A will
return $15 million into the reserves and
reserve funds. Offsetting that, the
budget adjustments require a draw of
$4.16 million. The net result is almost
$11 million being returned to reserves
and reserve funds, which will strengthen
our funding position heading into the
next budget cycle.
This slide highlights the projects that
are being closed. It covers the projects
recommended for closure. As I mentioned,
the total will be $16 million of
available remaining budget. Of that, $15
million is recommended to be returned to
funding sources while $1.1 million is
being recommended to be reallocated to
other projects where the work is still
required. The returns are broken down in
the report as well as here by
departments and funding sources. This is
a strong indicator of disciplined budget
and cost management by our project
teams.
This slide highlights appendix B of the
staff report. It sets out the project
budget adjustments as well as the
funding changes. These are adjustments
to active projects where scope, timing
or market pricing or funding sources had
to be changed to the to the original
approval and where council is required
to uh council approval. It's required to
realign the budget and funding is needed
for inyear capital budget additions.
As you can see from the top left top
left corner of the slide, we have
consolidated a number of capital
projects to streamline administration
and they have no financial impact.
The bottom left highlights the
recoveries from external sources as well
as proceeds from the sale of assets.
To the right, budget and funding
adjustments as well inear capital budget
additions are outlined in the following
slides.
Walking through the budget and funding
adjustments in more detail. The
adjustments identified on this slide
highlight the projects, the change in
budget required and the funding sources
that are being drawn or released in the
report. Collectively, these adjustment
results in a net draw of $4.16 million
from the reserves and reserve funds,
which is the amount included in the
recommendation.
As you can see on this slide, as a
result of favorable tender pricing
achieved through early tendering, the
budgets for four road reconstruction
projects can be reduced. And that's the
$4
million that's shown on the slide.
Moving to the bottom of the slide,
additional budget is requested for the
aerot truck due to market escalation and
for the completion of phase two of the
cultural center renovation.
Moving on to the next slide. Consistent
with the capital budget financial
monitoring policy, budget adjustments
approved by council or deleated
authority are highlighted in appendix C.
What you see on this slide and the
report are the projects that are
exceeding $100,000
which would require council approval.
This slide highlights the in-ear time
critical capital budget additions
identified since the adoption of the
2026 budget. These projects are needed
that require timely approval and they're
typically driven by emerging operational
service delivery as well as asset
management needs. As you can see on this
slide, there are four construction
projects being requested largely to
address asset management needs, achieve
procurement efficiencies and to maintain
project as well as service delivery.
The design of Brody House Park
that was a council direction from June.
So that has been included in this report
as well as an addition. And then last
but not least, the early implementation
of the tennis and pickle ball strategy
requires the negotiation of a commercial
lease agreement with Metro Links. So we
have included that um as one of the
budget additions here and this is to
ensure that we have the seasonal courts
that will be operational in the spring
of 2027.
This table highlights the status of the
open capital as of June.
After the projects are closed, the 186
that we just spoke about, we will have
482 open projects that are ongoing. And
as you can see on the slide, we have
spending to date of almost $140 million,
expected spend of another $82 million.
And then you see that the future year
figure on the far right corner reflects
the multi-year nature of much of our
infrastructure work. So those are
budgets that will be used in the future
years.
The recommendations of the report are
before you. Uh chair depala that
concludes my first presentation and I'm
available to answer any questions
related to this.
>> Okay. Thank you very much. Uh, okay.
Thank you for that update. So, uh, we
got a recommended motion on the floor.
Someone like to move that, uh, first
first speaker, Deputy Mayor Garvin Chan.
>> Thank you very much, uh, Mr. Chair, and
thank you, Miss Lee. I'm so touched. I'm
now back to meetings after the summer.
>> Yes. Uh, but thank you. This is serious
stuff we're talking about. Particularly,
we're talking about big money like to me
anyway. Uh, so I'm happily moving first.
Um, oh, you need is it only rel to
presentation, Mr. Chair, or you want me
to move recommendation?
>> I'd like uh the motion on the floor if
you're willing to do that.
>> I'll be happy to move the recommendation
A, B, and C. Um,
>> thank you.
>> Thank you for that. So, it's a motion uh
on the table. Um, thank you for the
presentation and it's always nice to
have u I like the word sherpress. Um the
only well not only the one of the
questions I have is through you Mr.
chair to director Lee um
because I don't want to just look at one
year this is only one year uh but how's
it compared to our prior years is that
seems to be a pattern that uh because of
very prudent and also technical uh
management of the capital projects um
that the city had
been experiencing uh on counter surplus
quite often. often uh from year to year
or this is quote unquote exceptional
year through you Mr. chair
>> through the chair to deputy mayor Chan.
So um it is a strong indicator of
discipline budget and cost management by
the project teams and I would say it is
a trend that we've experienced over the
last few years um especially so in this
report um because it is the first time
that we're presenting this in the year
of 2026.
So there there are more projects being
closed. That's why you're probably
seeing a a slightly elevated number, but
overall the trend is about the same.
>> Thank you. Well, that's the good news to
hear. So, so it's not just one year
wonder, but it has been I hear the word
trend. So, it's more than one year it's
been uh having the surplus. So, that's
great. Thank you very much to all staff
engaged in uh uh managing um the uh
projects and we are able to close some
of them. Um and relating to to that uh
on item C of the recommendation
now am I correct to interpret help me
interpret through Mr. chair from
director Lee. Um while B2 of the motion
is say returning money uh surplus to the
sources that have been identified but C
would mean net draw. It means new money
being drawn from
uh the reserve or is it something that
goes above and beyond what initially
what the capital funding might have been
allocated through M. Help me understand
through Mr. Okay.
>> Slides.
>> Oh, is a slide.
I'm going to take us back to slide
three. Uh, through the chair.
So, as as you've noted, Deputy Mayor
Chen, the $15 million is still returns
from the project closures. The $4
million is the net ask for the
additional budgets and then overall the
net return will be almost $11 million.
So, the 4.16 does represent a draw for
those projects.
>> Okay. Thank you. Uh so through Mr. Chair
uh director Lee would that mean this is
4.16
million to withdraw which meaning the
capital project now in terms of
projected estimated expenses would be
higher than what the initial allocated
you know maybe this year last year or
the year before last
three Mr. Sure,
>> Mr. Chair. That's correct. So, this
number represents the emerging needs
since the adoption of the 2026 capital
budget. So, this is over and above.
>> Okay. So, it's some plus, some gains or
some minor, so to speak. But thank you.
So, $10.9 million is the net being
returned, which is still a very good
number. Um the very last um question or
comment uh one of the slides is say 0.5
million if I see it correctly relating
to early implementation
of tennis and pickle ball strategy.
Um I know we're talking about money
here. Could you please elaborate a
little bit to the extent that you are
aware of? Director Lee uh is also one
before this I guess
at the very bottom there's something
about early implementation right there
exactly pennies and pickle ball strategy
early implementation I'm glad I still
remember correctly.5 million so any
uh help me or us understand um what sort
of early implementation may be
undertaking through Mr. here
>> uh through the chair um perhaps I can
start on this. So essentially that
budget amount is required for as you
noted the early early implementation of
the tennis and pickle ball strategy and
primarily for the negotiation of a
commercial lease agreement with
Metroinks so that we can enable the
seasonal um pickle ball courts to be
operational by spring of 2027.
>> Okay. Thank you. So the half a million
dollars is presumably for consultant
legal fees things of that nature because
sounds to me is primarily relating to
negotiation of that contract
>> through the chair. That's correct. Yeah.
>> Okay. Thank you. Thank you Mr. Chair and
thank you Dr. Lee and uh my move of the
motion stands. So we'll be look forward
to hearing from my colleagues. Thank you
Mr. Chair.
>> Okay. Thank you. So we have a motion on
the floor. Next speaker is uh councelor
Silvitz.
>> Thank you, Mr. Chair. Good afternoon,
everybody. It's great to be back. Um I
just have a couple of questions. First
of all, thank you, Treasurer Lee, for
very good report. On page on slide
seven, I just have an a couple of
questions. Um just referring back to
what Deputy Mayor um Chan was referring
to. We're talking about the West Gormley
property. Is that right? the for Metro
links
>> for the pickle ball
>> through the chair. That's correct.
>> That's correct. Okay. Thank you. I just
wanted to make 100% sure about that. Um
now, um very glad to see solar panels
being installed on Tom Graham. Um is
there any through to to through you, Mr.
Chair, or to our treasurer or to our
commissioner? Um is there any
possibility that we're going to do that
to more public facilities?
Commissioner
Not to put you on the spot, I'm just
wondering. It's just such a great idea
>> through the chair to councelor Silivitz.
Thank you for the question. We have done
a robust study of all of our facilities
and where we can and cannot facilitate
them. This is the one through that
analysis that came out on top as one
where the facility would best suit solar
panels. There's a lot of complexity into
determining whether or not a facility
can accommodate it without getting into,
you know, too many details.
>> Okay. No, that's terrific. Thank you
very much. I appreciate that. And then
just referring to the central library
roof replacement. Um I also see our CEO
Mr. Gman here and I don't know if he
wants to help with this particular
question. Um is this going to require
any further closure of the central
library through you Mr. Chair to the
comm commissioner?
>> Through the chair to council silvitz no
like any other facility where we replace
the roof. We do not require the closure
of a facility in order to rehabilitate
the roof.
>> Okay. Thank you.
>> Facility.
>> Thank you. And that'll be done while
we're also preparing the Dave Baris
Civic Square. It's kind of like the same
timeline.
>> Yes, that is correct.
>> Okay. Thank you.
And to if I may through you Mr. Chair to
CEO Gorman, not to put you on the spot,
would you like to give us an update on
the central library um renovations and
how we doing? I think it opened today,
didn't it?
>> Considering it is capital and
infrastructure
>> just uh half an hour, an hour ago, uh it
is amazing. I can't wait to show you
guys what we've what we've done is we
have recreated on the inside a modern
library of today. Uh it's going to be
stunning in the things we're going to be
able to do there going forward. It's
going to transform the city, I'm sure. I
often say that the city, we're the
center of the city. Um, and there's not
many places where the city can come
together, but now they have an amazing
space when they come together. So, we're
working on it. It'll be ready uh for all
of you to come and join us probably in
uh in January when it's done, but it's
open today.
>> That's fantastic. I'm I'm going to pop
by.
>> Yes, please do. Thank you.
>> Thank you very much.
And those are all my questions. Thank
you, Mr. Chair.
Okay, next speaker is councelor Shu.
>> Thank you, Mr. Chair, and thank you,
Treasury, and your team for your great
effort. And uh some of the questions
covered by my colleagues already. So, I
have only one quick questions. Uh I'm
happy to see that around 10 million uh
$10 million is being returned to reserve
and reserve fund with about $5.2 million
going back to DC reserve fund. Uh we
understand the city receives some
fundings from the provincial government,
but the DC shortfall could have a
significant impact over the next few
years. So would it be possible to put
even more of the surplus into the DC
reserve fund to prepare for the years
ahead? Is the $5.2 million the best we
can do through Mr. Chair?
through the chair to councelor Shu. So
the as noted in the report, the $5.2
million represent the DC funding sources
that were um the DC funding that was
originally drawn for growth related
projects and now that the projects are
completed, we will return them back to
source. So to answer your question about
whether we can provide more funding into
the DC reserve funds, um unfortunately
DC's are legislated, they're statutory
reserve funds and they can only be used
for the purpose of growth related
projects. The so the same way that we
can only collect from growth, we can
only spend it on growth. So we we
wouldn't really use another funding
source um
to top up the DC reserve funds.
>> So that means there's no way to put
additional uh surplus back to the DC
reserve fund. There's no other way under
the current regulations. Is right
>> because I'm I'm quite worried about the
DC shortfall in the coming years. So I
just raised this question
>> through the charity counselor shoot. So,
so there are mechanisms, but I think we
also have to think about whether we want
to go ahead with that because obviously
we have funding sources and reserve
funds established for different
purposes.
>> So, in topping up the DCs with other
funding sources, we're potentially
shortch changing other funding as well.
>> Okay. Thank you. Uh that's all my
comments and questions. Thank you, Mr.
Chair.
>> Okay. Thank you. Uh, next speaker is
councelor Davidson.
>> Thank you. Thank you for the report. I
do have a couple of questions. One is
the Metro Links um, pickle ball.
What is the estimated cost for that?
Because I I think like my suggestion
when I brought it forward was that we
have we utilize the space that's not
being utilized at the moment, but it
can't be at any cost. So, I was really
thinking low, but I like are we having
are we talking about massive amounts of
money for this thing? Like is it over
25,000 30,000? Like where are we looking
at the range? I know it was quite high
before. I know. I I just want to
publicly talk about like I I personally
I don't think it's coming back to
council, right?
Are you Mr. Chair? Is it coming back to
council? the metro links
>> uh through you Mr. here. Uh the cost I
think that's associated with the budget
that's in front of you on the capital
side is for those negotiations to take
place. Um there will be cost associated
with those courts because there's
certainly maintenance costs of involved
and uh and there are some costs that
we're negotiating in terms of uh the
land that those courts will go on. But
that's uh a Cole's note summary in open
session.
>> Thank you. um through Mr. Chair, but we
it's not coming back to council for
approval. Is that right? Like the
negotiation doesn't come back for us to
say yay or nay. I'm just worried it
didn't occur to me that it would be I it
occurred to me money would be spent, but
the it's only worthwhile if it's
economical to do that rather than
building something more permanent
ourselves. So, I'm asking what's the cap
on that?
>> Uh through you, Mr. Chair. Uh so we'll
um consult with staff uh in terms of
what will come back to council uh for
the agreement with Metro Links. Um but
we have direction from council at this
point to proceed
>> right. I I know I'm not sure it will
come back
>> right through you Mr. Chair. I I'm just
>> It'll come back through budget at some
point.
>> Yeah. Like I mean I know you you guys
think of all the angles and and if there
was some way that it would be so
expensive to use that that you would say
you know what for a little more we could
build something permanent blah blah
blah. That's all that's concerning me.
Um thank you. Um and my other question
is the solar panels. I'm happy we're
doing that. I just want to know for you
Mr. Chair when is that start to pay off?
Like that's a lot of money for
installation. Where's the electricity
going? And how many years will it take
till we're we've broken even and we're
moving on and actually saving some
energy money because we have solar
panels now or is it being sold
>> uh through the chair to councelor
Davidson? um as we've noted in in the
report is an estimated payback of 9
years and that's incorporating the um
the incentive that we anticipate of
$318,000.
So the total cost minus the incentive
we're looking at about 9 years for for
payback, right? So then you m So in nine
years it's it's gravy, right? We're
going to pay it off and then we still
get to get the energy and Okay, great.
Thank you. Okay, that's it. Thanks.
>> Great. Thank you. Next speaker is
Councelor Thompson.
>> Uh thank you very much and uh thank you
for the presentation and the report. Uh
just a couple of quick questions. Um one
of the things I noticed is that uh by
June 30th we had only uh expended
approximately 36% of forecasts. Is that
typical? like are are things generally
back end of the are the the later parts
of the year that we typically get our
expenditures.
Um that's my question
>> through the chair to councelor Thompson.
Uh short answer is yes and that's why in
the report we also estimate the
anticipated spend for the entire year as
well but perhaps commissioner Misaro can
add to that
chair to councelor Thompson build on
treasur's comments typically in
construction we do see most of the
invoicing come in towards the latter
half of the year even the first quarter
the subsequent year and because most
projects projects are multi-year
projects as well. You'll see that the
most of the money that the municipality
uh has currently unspent, you know, sits
within that, you know, one to four and
five year mark and generally everything
beyond five years is what is a lot
smaller in the in the remaining balance
of the city's open capital and in many
instances to take into consideration as
well. Uh a good portion of that is also
projects delivered by third parties. Be
it projects that the region is
delivering on our behalf where we fund
or items that we put into the capital
budget that are delivered uh by the
development community.
>> Okay, I appreciate that. Thank you. Very
comprehensive, too. Thank you. Um the
other thing that caught my eye uh was in
the report in uh the 2022 budget
uh we were looking at the replacement of
the aerial uh fire truck and uh at that
time the budget was 1.5 million and when
I look at the report today it's bringing
a revised budget of approximately 3.23
million. So that really that number
really jumped out at me. And at the same
time, I I I certainly understand where
we've been and where where we are today.
And I also understand where we might be
tomorrow. Um, so getting that uh aerial
truck in there, do we actually have the
opportunity to get that truck before
other imposing
uh types of expenditures could push that
number up even higher
>> through the chair? I'm going to defer
that to the chief.
>> Uh through the chair to councelor
Thompson. Thanks for the question. Um
that number is alarming for sure. We've
seen a lot of uh increases to the cost
of fire apparatus over the last few
years. Um exponential to be honest. Uh
so we have taken measures now. We've
been able to find uh a suitable truck
that's going to meet our needs and meet
the needs of the municipality. Um that's
almost ready. It's under construction.
It's about 80% build. We're actually
going to get it very quickly. We have to
jump now. And the recommendation that's
before you is to allow us to do that and
then avoid any potential other
escalations that we think might be
coming in the future with the climate
that we're in.
>> Thank you, Irene. Very diplomatic about
what other escalations might entail. Um
>> uh and I appreciate that. So yes, I I I
wholeheartedly support the direction
here and I appreciate that you provided
that clarification. Thank you so much.
Uh those are all my questions.
Okay, so that exhausts the speakers list
that I had and um for myself I just have
one question. Um I think it's fantastic.
We've saved almost $5 million by early
tendering or at least it was attributed
to that. Is it strictly the result of
early tendering on on those projects? Um
it it and
is are we going to get hurt next year
when we're we're we won't be able to
convene as a budget committee and we
won't be able to wrap things up in
December because I think the fact that
we're done in se in December and we're
getting out there first tender for
projects it's more competitive we're
getting better prices is that going to
be affected next year
>> through the to for the chair. Um so
definitely that with the timing of the
budget approval, it does mean that our
procurement process um or public
procurement process will start a little
bit later. Um, but I do want to point
out that staff are also working
diligently internally uh to make sure
that we're getting all the work done um
so that we can have all the documents
and every ready so that when the budget
is approved then we can go ahead and
make sure that we get to the market as
early as we can.
>> Great. Thank you. Okay. So um well it's
a significant advantage and u something
for us to keep in mind to try and
continue. It's the same every
municipality is in the same boat with
the elections and um you know if we get
get here quickly and get down to work
and we appreciate um financial staff um
getting all the work done behind the
scenes
um then be ready for when we do
reconvene as a as a council. So, uh,
that was my only question and we've got
a motion on the floor from Deputy Mayor
Chan. All in favor? Any opposed? That
carries unanimously. Okay, we move to U
business item 5.2, which is the 2026
year-end operating forecast and and also
again a presentation from GG Lee, our
director of financial services and
treasur. Go ahead
and
>> thank you. Turning now to the second
report which is the year and operating
forecast. This report provides the
mid-year results and the projected
year-end position for both tax supported
as well as the rate supported
operations.
In this section, I'll walk through the
operating forecast, the main pressures
that are on the tax supported budget,
the offsetting opportunities we've
identified, and also provide an update
on the rate supported outlook for water,
wastewater, and storm water. The
objective of the year and forecasting
process is to provide visibility and
transparency into the emerging budget
pressures across the organization,
enabling staff and leadership to
identify mitigation strategies and make
informed adjustments as needed.
Staff are expected to take mitigating
actions where appropriate to ensure that
the city remains aligned with the
approved net operating budget by year
end.
This table sets the sets out the
mid-year position by department. At
midyear, the total tax supported budget
is almost $80 million and it shows an
unfavorable variance of almost $4
million or 105% of the budget. The
largest pressure sits within community
services and in planning and building
services where mid-year spending is at
109 and 142% respectively. This is due
to high winter maintenance costs, fire
and emergency services staffing as well
as lower development revenues and these
are partially offset by some of our tax
related revenues.
Importantly, the year and forecast
column at the very far right shows the
total returning to 100%.
and remains aligned with the approved
net operating budget largely through
these corporate accounts that I
mentioned and the offsetting
opportunities that I'll cover shortly.
This slide highlights the key pressures
as noted on the slide. Development
planning revenues are forecasting $2.5
million below budget. This is reflecting
a slowdown in construction activity and
lower building permit volumes. staff
continue to monitor development activity
and are advancing service improvement
initiatives as part of 2026.
Also noted on the slide is their winter
maintenance costs that are $1.5 million
over budget following uh a very busy Q1
in 2026 when it comes to weather.
Fire and emergency services staffing is
approximately $1.2 $2 million
unfavorable and this is largely driven
by overtime shift premiums and health
related absent to use them.
Just going through the rest of the
slide, recreation programming,
sponsorships and rentals are lower by
$700,000.
And last but not least, facility
management is about $400,000 higher,
reflecting the maintenance needs of our
aging facilities.
Offsetting those pressures, we have a
number of opportunities. The tax related
penalties and interests are forecasted
to be $2.3 million higher based on our
higher outstanding balances.
Assessment growth as approximately $1.3
million and this is due to the timing of
budget approval and the final impact
updates that we received after budget
approval.
As noted on the slide, we are
anticipating approximately $800,000
in higher investment income. And this
largely is resulted from our shift into
short-term securities
as we have in um the prior years. We are
expecting $700,000 in payment in L of
taxes from the York Region Orlando Drive
transit property. So I understand the
discussions are still ongoing between
the province and the region. Therefore,
we continue um to be able to collect
this as an additional revenue.
Last but not least, insurance premiums
are lower than what we have forecasted
and budgeted and this is following our
move to a pulled program with York
Region and other municipalities.
And just a quick update, we also have a
signed service agreement when it comes
to that. Now
on the rate supported side, water
wastewater is forecasting a 7.2 million
surplus and the largest driver related
to that is that one time almost $6
million credit that we're getting back
from the York region and it's related to
the inaccurate billings from 2025.
Volumes are also trending above budget
this year due to the dry summer,
generating additional revenues, and
they're partly offset by higher water
purchases.
As noted on the slide, the storm water
management fund is forecasting
uh $140,000 in surplus, and that largely
has to do with favorable property tax
classification changes.
the recommendation on the report of the
report it's it's highlighted on the
slide Mr. Chair that concludes the
second presentation.
>> Okay. Thank you very much. Uh so we'll
deal we'll deal with it again in the
same manner. Uh we'll have questions and
and a motion at the same time. Anyone
want to move the recommendations in the
staff report? Uh Mr. prayer. Go ahead.
>> Well, thank you very much and um thank
you very much uh Treasurer Lee and all
of your staff and and all of the the um
the folks that work here to to help put
this on because I know this is
absolutely a team effort. Um I um I I
don't really have any questions. I I I
realize though as I'm listening to this
presentation and all the others that
we've heard up to this point how
unbelievably complex this job is in
balancing something as large and with so
many moving parts as a municipal budget.
And I just I I really it never ceases to
amaze me ever since I've been on this
council. Um, and you know, being that
we're in the environment that we're in
right now with u that little election
thing coming up, um, it it really um,
amazes me when I have discussions with
people at the door and and and so on
that just how complex some of these
issues is, issues are. It's not just a
matter of, hey, I'd like to pay less
taxes. I mean, we all would like to pay
less taxes, but the reality is, you
know, in this particular report, um, you
know, mother nature throws a whole bunch
of snow at us and and, you know, and
we're going to be over on our winter
mainten maintenance budget. And there's
all kinds of other variables that we,
you know, we don't directly um, control,
but yet at the same time, we're planning
on mitigating strategies all the time to
make sure that the the money that's
spent in the corporation is spent
wisely. and this update is a perfect
example of that. Although there's many,
many, many other perfect examples every
time we're here at council listening to
the staff present. So, I just want to
say thank you. Um, you know, I think
this is, um, the main thing that I get
out of this is is, you know, every year
when we have this year-end operating
forecast report and then the the final
report at the end, I don't think we've
ever been in a situation where there's
been a substantial deficit even with
some of the variables. And I think that
speaks to the unbelievable careful uh,
management that we do around here. And
you know, we've had a couple of years in
the last little while where we've had
really substantial surpluses due to, you
know, frankly, it was a market windfall,
you know, for the most part. But, um,
and that's great. I mean, if that
happens, you know, bring it on. But we
want to make sure that we are managing
our finances as carefully as we possibly
can so that we're mitigating any um any,
you know, downsides that happen. And,
you know, it's very, very difficult
particularly in the economic environment
that we're in. and then you throw some
natural um weather stuff at us and it
becomes even more difficult. So, I just
want to say thank you very much and um
I'll leave it at that and happy to move
the motion.
>> Okay, great. Thank you. So, with the
motion on the floor, the next speaker is
car uh councelor Davidson.
>> Thank you. And through Mr. Chair, thank
you for the report. Um these are pretty
minor questions, but the sports dome, it
says it's not quite utilized 100%. Um
just wondering if
I don't know if that's a huge deal but
we do hear from um racket sports people
is there any thought or opportunity in
the future to make sure it's filled up
by offering other things besides field
sports in the dome something like
badminton or tennis
>> uh through you Mr. Chair. So, we are
always uh re-evaluating our program
offerings and trying to uh maximize our
fill rates to the best ability we can.
Uh this year for the Sports Dome is a
bit of a transition year because as you
might recall, this is the first year
we've had the Sports Dome open all year
round. And so that's that's why our
forecast is off a little bit because
we're speculating into the future
without any real good precedent to base
that on. Um so we we will uh hopefully
get that adjusted in the future.
>> Oh, great. Thank you. That seems fair.
Um, and the other one I sort of caught
my eye through, Mr. Chair, is 1.2
million over budget for fire and
service, mainly because of um staffing
levels, operation continuity. Um, I
think last year there was maybe a half a
million dollar overrun. I think if I
recall correctly, it was regarding um
dispatch.
My question is that seems high as a as
off. So what if anything can
uh emergency management do to foresee
these these overruns? I realize we're
dealing with people here, but and and I
don't know how to run a fire department,
but is there ever a model where like
there's four floater or five floater
fire members of the fire service who
fill and plug holes rather than it being
expensive overtime. I I don't know if
that's even possible, but I know for
example in schools now they'll have
full-time substitute teachers to fill in
because there's a lot of absenteeism. So
just ask if there's a better way to
management manage this. So it's not an
overage annually.
>> Uh Mr. Chair, to the councelor, it's
something we struggle with. Um you'll
notice in the report that um WSIB has
mentioned which are workplace injuries.
So that we've seen a real increase in
that. Uh currently we do not have an
overstaffing if you want to call it
that. Um there may be some options
coming forward to council in the next
little while to help us address this
overtime issue. It has been going on for
several years and it's not getting any
better. Um, we're not the only ones.
It's not just Richmond Hill dealing with
this. All larger municipalities are
dealing with this and trying to take
action on staffing levels to
accommodate.
>> Thank you, Siri, Mr. Chair. So it seems
to me that like even asking for more
positions to offset the overtime seems
more frugal to me. But can you explain
how just briefly how how do you how do
you decide how many folks you need every
year? And are are there any efforts to
offset overtime by maybe taking one or
two more full-time staff so that there
are people to plug holes maybe even just
for that if you understand what I mean.
Uh yes, through your chair to councelor
Davidson. We
we do our best to do that. Um there may
be some staffing recommendations that
come forward to help us address this
this issue. Uh it is a hard thing to
manage because we don't know when people
are going to be off and like I said
there's been a real escalation in the
last 18 months to two years in
um workplace injuries.
So, we are trying to find a way to
accommodate those absences through
potentially additional staff.
>> Okay, thank you.
Those are all my questions.
>> Okay, thank you very much. So, I Oh,
councelor tree.
>> Okay, thank you so much. Thank you our
directors for your hard work. So, I just
have a very simple one. So based on
current status do we uh do you have a
maybe a high level summary how many
supplies we have here
from all different operations. Do we
have a surplus here or
>> surplus?
>> Uh through the chair to counselor tree
if I may repeat the question you're
asking about whether we're anticipating
a surplus.
>> That's right. Uh Mr. the chair again um
no we are anticipating to come in and
align with the budget.
>> Okay sure I'll wait for the end of year
when this officials budget in karma I'll
see what is our operation final uh
numbers. Thank you.
>> Thank you and and councelor Leu
>> thank you very much. Thank you for the
um the report. Um just a few quick
questions. What happened to the aquatic
uh program?
through you, Mr. Chair.
>> Uh through you, Mr. Chair. Um you're
referring to the slight underage in
program.
>> Yes. So, we believe what we're seeing is
an effect of the economy with uh
residents and people with less
discretionary income. Uh recreation
programs are usually one of the first
things that people start to spend a
little bit less on. And we think this
year we're starting to see that impact.
>> All right. and they choose not to learn
to swim and Okay. All right. No, that's
that's that's that's just fine. Um um
talking about that um so the uh tax
related revenues, so there's an increase
of penalties and interest. Is it because
the residents have trouble paying taxes
on time through Mr. Chair?
through the chair to councelor Leu. So
the
short answer is yes. So as much as we've
started with our tax collection process,
we are noticing and it's not just
Richmond Hill. Um overall as we also um
have these discussions with other
municipalities to understand our
situation as well. It is definitely the
the the trend that we're seeing is that
overall the tax rear are increasing.
>> Yeah, that's that news. Um I think it's
economy related. Um the other thing is
in terms of the uh winter maintenance.
Um so I I saw on the news that you know
because of the super El Nino uh we're
going to have a very warm winter.
Is it going to
>> All right. Sorry.
So, is this is that going to change how
we budget the winter maintenance?
Did I say something wrong?
>> Is does that change how we uh budget for
winter maintenance?
>> Great through you, uh, Mr. Chair. So,
um, our budgeting, all of our budgeting,
winter maintenance included, is is our
best estimate. Um, and usually those
estimates are based on averages of the
last, uh, 3 to five years. So, we're
it's just we're trying to hit the middle
right here and and not be over or under
by too much. We're trying to hit the
middle. Um so, I I I think the answer to
your question is no, it's not going to
change how we budget. Um it's just the
weather changes how far off our estimate
is.
>> Yeah. Got it. Yeah. Thank you. Rather
have a surface next year. All right. Um
I I think my uh my last one is uh um I'm
aware that the school board is raising
their uh gym rental fees for a lot like
double. Um I I don't know if it's going
to increase the demand for our community
centers. Um just to want to, you know,
throw it out there. Um I don't know how
the rates of the community centers
compared to the schoolboard. um but I
think is now is is is comparable. So I I
expect a a big a huge demand um for for
gym rental for our community centers.
That's just a comment. So thank you very
much.
>> Okay. Thank you. And uh we'll we'll go
to a second round. Mayor West.
>> Thank you. Uh so just a couple more
quick questions then based on the
discussion we've had. Um I I want to be
clear like one of the things I was I I
kind of implied in what I said in my
first round was that it's also really
important when we're doing a budget like
this that we're not overcolcting
uh above what we need. So for example
with winter maintenance you know we
don't want to collect more than we
ultimately need for winter maintenance
because that means that we're collecting
more from the taxpayer. So, um I think
it's, you know, every year I I mean I
remember a couple of years where we've
had surpluses that are very very small
and that's actually great because unless
the surplus comes from a windfall
because the market did far better than
we thought which is not coming from the
taxpayer um then you know a zero is a
good thing like not under not over but
somewhere very very close to the line
and snow removal is a good example like
we can't predict what mother nature's
going to do some years we're going to
have more. Some years we're going to
have less. But, you know, we don't want
to be predicting that we need a whole
bunch more and then not need it because
then it goes to a surplus and that just
means we've overcolcted from the
taxpayer. We do not want to be adding
more pressure. But on that note, am I
wrong to assume uh that when like we
have reserve funds for snow clearing and
am I wrong to assume that in years where
the snow clearing budgets a little high,
we put it towards the surplus and when
winter maintenance is uh a little low
then we take it like we if we've
overspent on winter maintenance, we take
it from the surplus in the reserve fund.
Is that is that how that works now or
are are we doing it differently?
>> Through the chair to Mayor West, we did
have a snow removal reserve uh which we
did deplete in 2025.
>> Okay.
>> So, as a result, any overages would have
to um obviously be part reviewed as part
of the operating budget and it would
actually be the tax rate stabilization
that would be the the default funding.
>> Okay. But that's my point is that I mean
when we have a situation like that there
is a fallback position. So it reduces
the need for us to collect more than we
are likely going to need because if we
collect X amount but we spend a bit more
than X amount the additional surplus
would come from a a reserve fund as
opposed to a um another fund uh like a
tax rate uh generated fund and that
reserve fund over time will be um added
back to as needed. like the tax rate
stabilization is a good example of one
where because we don't rely on that
anymore and haven't for I believe the
last four years. Um that reserve fund is
now growing back to the point where it
should be as opposed to where it used to
be which was getting very depleted. Um,
and again, that's just another example
of really prudent and wise fiscal
management that we we are seeing in
every single budget. And that, you know,
I think sometimes uh the public and and
even us on council sometimes take it for
granted that we, you know, that we're
not doing those kinds of things, but we
are. It's really it's really good sound
management practices. And so I I
appreciate that. So, thank you.
>> Thank Thank you. So, that exhaust
speakers list. Um, I I just want to make
a few comments before we vote on the
item. Um, and and I I just want to thank
all of the people that uh have worked
together for the last four years on on
this uh budget committee. We've we've
we've passed four different budgets.
We've faced all sorts of adversity and
challenges and and transitions and you
know unlikely events that that we that
were unforeseeable that were uh met and
challenges that that were overcome. And
I'm I'm really proud of the team, the
senior management team uh led by our
city manager, Darlene Johnson, our
corporate services commissioner, and um
of course uh our treasurer Gigi Lee,
who's who's been there answering all our
questions, breaking it down for us over
the last four years. and your entire uh
financial services team that that has
has has done a great job. Uh this this
will be our last meeting. So just before
we make the call to vote on this last uh
item, um I I just want to express my
thanks. It's been an honor and um a real
pleasure to serve as as the budget chair
for this past term. So uh with that,
I'll call the vote on the motion on the
floor. All in favor?
Any opposed? That carries unanimously.
Thank you very much, committee.
>> We have one more vote. Thank you. Deputy
Mayor Chan, you wanted to move for
adjournment.
>> I'll be happy to move for the last
motion for this budget committee on
this. Thank you.
>> Okay. Any discussion on adjourning this
this meeting and this term of the budget
committee? Oh, I I do uh before we
adjourn want to thank uh Mayor West
because um he he could he could just
impose a budget upon us. This is this is
we are making recommendations to him and
he's he's opted to proceed in the manner
that we have and he rightfully deserves
the last word. Mayor West.
>> Well, if you're going to thank me, I'm
going to thank you. Um, I also do want
to say thank you uh, regional local
counselor Dalo for stepping up and being
the budget chair from the beginning of
this because it really uh has been very
helpful and um, I realize legislatively
that the the mayors that uh, in many
municipalities now have the
responsibility for the budget, but it
has been great to work with you and your
knowledge of all things budget has been
very very helpful and I really
appreciate that as well. So, thank you
very much for not only chairing the
meeting um but for continuing to to take
on the same role as budget chair that
you have since the beginning. So, thanks
a lot.
>> Okay. Thank you for thanking me,
thanking you. All all in favor?
Any opposed? That carries unanimously.
Thanks.