BIA Reviews Main Street Conversion Plans - 16 Jun 26
Hamilton · June 17, 2026
Sound check. One, two, three. Sound
check. One, two, three.
Check. One, two, three. Sound check. 1 2
3.
Good morning everyone.
Um,
we have corn present. So I would like to
call this meeting of the business
improvement area subcommittee to order
for Tuesday, June 16th. Please be
reminded that all electronic devices are
to be switched to a non-audible function
during committee meetings. We begin with
a roll call. Please indicate your
presence when I call your name. I have
regrets from counselors hang and Paul's
councelor Moren Wilson.
Uh Susie Braithweight International
Village also sent regrets. Tracy
McKinnon from Westdale,
>> present.
>> Jennifer Madden from Ancaster,
>> present.
>> Adrienne Meckley from Hess Village,
>> present.
>> Susan Penny from Waterdown.
>> I am here.
[laughter]
>> I love the enthusiasm. Doris Sanchez
from Concession.
Betina Shoreman from Lock Street.
David Taylor from Dundas.
>> Good morning, present.
>> Emily Walsh from downtown.
>> Good morning. President
>> like I see her face. Uh
Stephanie Wiler from Ottawa Street.
>> Hey everyone.
>> Myself from Barton Village
and Brennan Weton International Village.
No.
Okie dokie.
I will now read the land
acknowledgement. The city of Hamilton is
situated upon the traditional
territories of the eerie neutral Honend
Hodneson and Missagas. This land is
covered by the dish with one spoon
wampom belt covenant which was an
agreement between the Hnoson and
Anishnabek to share and care for the
resources around the Great Lakes. We
further acknowledge that this land is
covered by the between the lakes
purchase 1792 between the crown and the
missagas of the credit first nation.
Today, the city of Hamilton is home to
many indigenous people from across
Turtle Island. And we recognize that we
must do more to learn about the rich
history of this land so that we can
better understand our roles as
residents, neighbors, partners, and
caretakers.
May I have a mover and seconder to
approve the agenda as presented?
Moved by Jennifer, seconded by Emily.
Are there any amendments from committee
members to the agenda?
Going once.
Um,
if no, then can I see a show of hands to
uh
approve the agenda?
That motion is carried.
like taking notes at the same time here.
Okay. Are there any declarations of
interest?
Not all at once, you guys. Uh seeing
none,
may I have a mover and seconder to adopt
the minutes of the May 19th, 2026
meeting as presented. Moved by David,
seconded by Tracy.
Any discussion on the minutes?
Seeing none, please indicate your vote.
Looks like that motion is also carried.
[snorts]
Okay.
Uh items for information for those
providing presentations today. Please
remember the presentations are limited
to 10 minutes. First, we have item 7.1,
overview of the Main Street two-way
conversion and its impact on business
improvement areas. I would like to call
upon Brian Hollingsworth, director
uh engineering services to please begin
your presentation.
>> Thank you for the introduction.
Zoom up here.
Okay,
>> there we go. Okay. Uh, as mentioned, uh,
Brian Holler, director of engineering
services for the city of Hamilton. Uh, I
also have with me, uh, Shane Given, who
is the project manager who's been
leading, uh, over the past, uh, couple
years the design for the Main Street
project. And we have Ed English who's
manager of construction whose team will
be uh implementing this when it gets
going. Uh thank you very much for the
opportunity to present on the Main
Street 2A conversion project or as we're
calling it now the Main Street uh
revitalization and redesign project. Um
you may wonder uh why we um opted uh to
come to the whole BIA committee uh for
this what might seem as a localized
project but we see it as an opportunity
uh to kind of socialize uh a project
that will have uh citywide impacts.
Um, we also see it as an opportunity
perhaps to maybe not in detail in the
meeting, but draw on the experiences of
different BAS uh through their major
construction projects or pending
construction projects. Uh, Lock Street
comes to mind that was done a few years
ago. Uh, there's a a very big one going
on underway in Waterdown with the bridge
uh 451, Grindstone Creek replacement.
Uh, and Barton Street uh will be uh
well, the resurfacing will be starting
soon. So all these kind of have have
lessons learned and we just see a
two-way dialogue as as being quite
useful. So my presentation will be
fairly short. I'm going to provide an
overview of the project. Talk about some
related ongoing projects which includes
the water main lining project which is
happening as we speak. Um talk about uh
how some of the things that we envision
doing uh for this project to mitigate
business impacts and then uh share some
brief lessons learned on on other
projects. Um so the project uh
as mentioned we're calling it the main
street renewal and redesign project
because it is a major uh project that
will um go from Dunder Avenue all the
way to the delta in the east end. Uh it
it involves road rehabilitation,
resurfacing, two-way conversion, safety
improvements, and uh a lot of other
things that I'll get into momentarily in
this presentation. Uh the two-way
component was directed by by council in
2022. Uh and since then we've been
working uh to bring the the project to
fruition and we are almost there.
[clears throat]
So the project as mentioned will will
include full resurfacing. Uh anyone
who's driven on Main Street today uh
around Dendern Lock uh will uh not
dispute the fact that it needs
rehabilitation. Uh it'll include
rebuilding of all the the cur what we
call curb ramps. um to modern standards.
So, they'll include the urban braille
and the the uh tactile warning strips.
Uh it'll include enhanced cycling
facilities between Victoria Avenue and
Sherman Avenue. Uh all of the traffic
signal infrastructure u not necessarily
related to the two-way, but it will be
upgraded because it is decades old.
There's going to be some street lighting
improvements and um the of course the
two-way conversion to to two-way flow uh
similar to James and John was done
[snorts] many years ago.
the in terms of the project timelines,
uh we are basically wrapped up the
detailed design and we're preparing the
tender. We're going to pre-qualification
to make sure that we get uh the best and
most capable contractors bidding on the
project and we expect to award uh the
work in um in summer for September
construction.
I just wanted to touch on the uh uh the
water main lining project. So, uh,
you'll see that the road is, uh, highly
impacted as we speak. Uh, what's
happening there for those that are
interested is we're basically, uh,
cleaning out and relining the the, uh,
local water man. Uh, and we're doing
that deliberately to make sure that
we're not ripping up the road again come
5 years. So, uh, that will extend the
life of that water man for, uh, many,
many decades. And I, I think, uh, when
complete will be, um, a much appreciated
project. But it has certainly caused
some traffic impacts.
[snorts]
Uh the design, I should mention that the
design is now uh public. Um it'll look a
little bit different than what you see
on the screen here. Uh uh there's if you
just Google Main Street Revitalization
Project, you'll come up with something
we call story maps and you can kind of
zoom into different locations and and
see what we're proposing. But for the
purposes of this meeting, just to inform
the discussion, I thought I'd just uh
summarize it very briefly. So from
Dunduran to Victoria, essentially what
we're looking at is uh maintaining three
lanes uh going eastbound and and one
lane going westbound. Um it should
provide a lot of benefits in terms of uh
improved uh traffic circulation. Uh also
um achieve some of our safety objectives
in terms of uh calming traffic speeds a
little bit. Uh we see that third lane as
providing some flexibility in the future
for things like on street parking or bus
lanes. [sighs]
uh Victoria to Sherman. Uh this will be
where we're um kind of turning it into a
real cycling facility uh with cycling
facilities on on both sides of the
roadway all the way from Victoria to
Sherman. Uh that will have some impacts
on on parking. Uh but overall uh it
should be a much more complete street uh
when when finished.
And then the the easterly segment uh
where it's a little bit more residential
in na in in nature. Uh we opted for a
design which carries two lanes
eastbound, one lane westbound and uh a
lot of curb extensions like what you see
in green here uh and greening
opportunities as well as on street
parking.
[clears throat]
Um this construction staging uh we will
be breaking it into different stages.
So, the first stage will be uh going
along and repairing the curbs and
sidewalks. Uh a lot of them are in
disrepair. It won't be a full sidewalk
uh replacement. We'll just be doing the
work that is needed. Uh I mentioned the
curb uh ramps. Um installing all the
curb extensions to the east, the cycling
infrastructure, and the underground
electrical. So that will be kind of
they'll just move along along the
corridor and uh close close a lane uh to
get it done uh and prepare the prepare
the road for the next phase uh which
will be uh milling and paving and
resurfacing. So some of you may have
experienced this. We did a section on
King Street uh through the downtown uh
last year. Uh I think it was done in in
a weekend. Uh this is a much longer
corridor, so it'll take take a little
bit longer, but um fairly um I won't
call it a simple process, but it'll
it'll move along quickly throughout the
corridor. Uh we will be looking at some
night work to minimize impacts to to
local businesses, and we'll be keeping
uh lanes open for uh transit and other
vehicular needs uh throughout this uh
paving process.
And then the final stage will be the
actual um energizing the signals and
opening it up to two-way traffic.
[sighs]
In terms of um business impacts, uh
there's there there will probably be
many um you know at the high level just
changing the corridor in terms of adding
the new direction of travel uh adding
active transportation facilities and
changes to parking uh will impact
businesses. Uh there will be changes to
access as well. Um we do envision that
all driveway access that's there today
will be will be maintained. Uh some some
movements uh will be prohibited. Um for
example, left turns across three lanes
of traffic. Um we're we're
[clears throat] looking at restricting
some of those movements at unsnalized
intersections. And we'd be happy to meet
with um uh the affected BAS to explain
uh things in more detail in a future
meeting. I think that's being planned.
Um the I I keep mentioning this, but you
know, as we've experienced from other
two-way conversions, the the the two
directions of travel um albeit a major
change does open up a lot more
opportunities for businesses and
accesses. And you can um confirm or or
deny that. But I think our one-way
streets are not conducive to um you know
helping people get to get to businesses
when they need to and a lot of uh re
unnecessary routing and then of course
the construction impacts which I've gone
through which hopefully we can uh
minimize but there there certainly will
be uh localized closures in some cases.
Uh moving on to the consultation and
engagement. Uh we have put a lot of
effort into things and they're starting
to roll out. I mentioned the website and
story map. Uh our our colleagues in
communications and economic development
have been uh tremendously helpful on
this project. Uh we're actually uh
dropping off postcards as we speak to
all businesses along the corridor of the
businesses highlighted in the map here.
So, um, maybe you'll start hearing soon
that that some of your businesses are
receiving those postcards. It includes a
QR code with further information and
directing people to the website. Uh,
Economic Development has has created an
Invest Hamilton web page uh with
targeted outreach and materials for for
businesses. Um, I think it's hopefully
will be very wellreceived and we'll
continue the the engagement and
consultation throughout the entire
summer prior to construction.
Just rounding out the presentation, some
of the lessons that we've learned uh
from previous projects uh is to consider
business operations uh and needs early.
Um uh that's kind of why why we're here
now. Um the project won't start till
September, albeit um oh, somebody can't
hear the speaker. Albeit um there are
impacts due to the water main lining and
we we we respect that. uh work with all
the businesses to mit mitigate impacts
where possible, provide clear and timely
information. Uh we're looking at some
signages, some enhanced signage to
indicate that businesses are open during
construction. And you know, we're we're
open to any other uh suggestions that uh
folks uh think would be helpful
in including suggestions from other
other BAS who might not belong the main
street corridor. So that concludes my
presentation. Um, I apologize to the
person who said they couldn't hear. Um,
but, um,
uh, happy to take any questions.
>> Are there any questions for Brian?
>> Adrian. Yeah.
>> Can we see the timeline map again? um up
your slide
[clears throat and cough]
um based on based on this slide um is
construction the start of construction
and then what is the estimated
completion?
>> Yeah, so [clears throat] our our our
current target is to have construction
underway or the tender be awarded in
September of 2026.
uh that's still an aggressive target. We
you know the tendering process does take
uh some effort but the whole team is uh
aligned around that start timeline and
then we envisioned that it will uh take
place uh in the the three stages that I
talked about uh and be completed by the
end of 2027. I should also mention that
we're breaking it up into two tenders uh
largely because uh it's a it's a it's a
big project and we see having two
contractors kind of one starting at
Denduran and then another starting at uh
Victoria both working eastwards uh will
will help minimize the overall duration
for the project.
>> Just another question regarding that. Is
it fair to assume that unrelated to this
but related LRT construction cannot
start until this is finished?
>> We're working closely with with the LRT
team. Um they're developing their uh
detailed designs and and phasing plans
as we speak. Um, I think there will be
opportunities to make sure we're kind of
offset, but at this point, um, you know,
we think we'll be done before they get
the the majority the the larger
components going.
Um, and to answer your question, no,
[clears throat] this this Main Street
2-way project uh is not delaying LRT
construction.
Uh Susan
um just from experience in waterown I
know that uh it on this timeline it
talked about some public engagement back
in 2022 and 2024. Um I'm not sure if you
are planning to get particularly with
some of the impacted BAS and other
people in that area. Um, if you have any
engagement planned on what that tender
looks like before it goes out because we
did run into some problems that the
public consultation here was done after
the tender was awarded and there was
very little opportunity to change or add
to or consider some of the um the issues
that had had real impact here in
Waterown. And then that meant either
things that weren't able to be added
because the project had already been
awarded as designed or that things had
to be changed and ended up costing more
money. So that's part one of my question
uh for those uh people that are most
most in that area that might want to
have a little bit of um consultation on
what that tender actually looks like.
And then just as an aside, the open for
business signs were promised to Waterown
and we had several emails reaching out
and we've never seen an open for
business sign come to fruition here in
Waterown. So, um those are just two
things based on our experience with the
bridge project.
>> Uh through the chair, um good suggestion
for the the first one. Um we are meeting
hoping to meet with the downtown BIA and
international BIA who are uh most
affected by this project and kind of
talk about you know things like
construction staging and and and get
their input. So I think that's that's a
good suggestion. And in terms of the
open for business sign um I have Ed
English who might be able to comment on
that or we can where we can have a
separate followup.
>> Yeah.
Okay, thank you for that insight, Susan.
Are there any other questions?
Emily,
thank you. Um, through the chair, do we
have any idea of what the holiday season
will be looking like and what kind of
construction will be happening uh during
those months?
Uh we'll likely still be in the concrete
um repair of curb and sidewalk and uh
intersection improvements as far as
traffic lighting goes in December.
>> Okay. Thank you very much.
Okay, if I can pass the chair to Susan
real quick. I have a couple of
questions. Um, [clears throat]
is there intention, just out of
curiosity, to uh recynchronize the
lights? Um, I think it's a well-known
fact that if you drive a certain speed
down Maine currently, uh, you hit every
green light or every red light on your
way, is there intention to to do that
post construction
>> uh, through the chair? Yeah, they'll all
be rettimed. They'll have to be rettimed
because of of the add the new direction
of travel. Um, they they were actually
de
uh synchronized uh as part of the 2022
project. um whether to the the degree
that was noticeable is is
uh up for question based on your comment
but but they were synchron des
synchronized to slow down traffic.
>> Fair enough. Thank you. As Barton
Village I don't often travel Maine if
I'm honest.
Um co second question for you is uh you
did mention there was going to be some
lost parking. Are there plans around um
recovering some of those spots?
uh through the chair. Um the there will
be losses in parking um uh including
through International Village just
because of the new lane of travel. So
the the one westbound lane can't serve
as a parking lane. Uh we're still
looking at opportunities for some uh
pockets on the the south side. Um that's
not possible where there's a cycling
lane. Um, I think there will be also
loading impacts as well because right
now you can um, you know, just there's
three, four lanes. It's it's pretty easy
to to pull over and do loading. So,
we're we're we're cognizant of that.
Um,
but that's part of the that's part of
the two-way the two-way project. So,
it'll have to occur on side streets, uh,
off streetet parking lots, etc.
>> Okay. And and I I well that's what I was
going to say too is that um I think it's
important to remember that um until
recently parking was banned along in the
peak periods along the entire corridor.
>> Fair enough. I'm I'm sure that those BAS
that are impacted from that will have an
interest in regaining um some of their
on street parking revenue.
Um
my third question if it's okay is um
obviously Barton anticipates some of the
overflow traffic um as the impacts
happen along Maine um and you mentioned
uh the shave and pave situation that's
supposed to be occurring um beginning
relatively imminently. Um,
and maybe this is something we can take
offline. I have some some questions
around uh specifically through sort of
the Victoria to Wentworth stretch um
where our lovely medians exist. Um
whether or not we can address some
issues there because um it's my opinion
that uh we would not be prepared for
that increase in traffic through that
corridor.
Uh
so uh yes we are looking at the staging
and the overflow impacts. I would note
that uh right now um you know traffic's
basically down to two lanes sometimes
one lane between Dunduran and um uh
McNab. Um that's a little ways from
Barton Barton Barton Village uh and
Wilson Streets down as well. So by the
time this starts up um the water main
line lining project which has
significant impacts will will obviously
be done. Uh Wilson Street I believe will
be largely wrapped up. So and your uh Ed
can talk about your Barton Street paving
but that will be um pretty much complete
as well.
>> Great. And oh, and one other point too
is that uh during during the
construction of the main street um
renewal project uh and I can comment on
this, we we will be leaving lanes of
traffic open. So it won't be like a uh a
lock street or a York Boulevard where
there's complete lane closures.
>> Wonderful.
>> Yes. As as Brian had mentioned, the Main
Street uh water main lining project will
be done uh before the Main Street
two-way conversion happens. Wilson
Street uh and Sherman will be completed
before the two-way conversion begins in
September. And likewise, Barton will be
completed
um we anticipate Barton Street will be
completed about midepptember if not
sooner. So, all of those projects will
wrap up before the main street uh
commences.
>> That's good news. I'm sure there's lots
of folks that are looking forward to the
end of some of those projects
>> and and the idea um
the way that the project is going to be
staged and the phasing within those
stages.
We'll do one side of the road first. So
the entire road isn't isn't being chewed
apart. We'll go along on let's say the
south side first and do all of the
intersection work halfway across. So
there will be two lanes open on the
north side and then likewise when the
south side is done we'll move traffic to
the south side and commence work on the
north side. The last thing we'll do
would be the shave and pave uh and line
painting. So, we're hoping to
have access for each and every business
for the full duration of the project.
Everybody will have access. Uh there may
be there may be times where perhaps into
a parking lot if it's a if the sidewalk
happens to be damaged, we'll be able to
stage uh the replacement of the curb and
sidewalk so that you can still access
half of the uh half of the driveway, get
into the parking lot uh while the other
side is being redone and then switch it
over. So, we anticipate there won't be
any problems with that.
>> Wonderful.
>> Tracy.
>> Okay. I'm going to take the chair back
from Susan. Uh Tracy,
>> thank you very much um through the
chair. Apologies if you had mentioned
this, but we had some audio issues, so
I'm not sure if PR had mentioned that or
not. Um just wondering if the um two-way
conversion is going to stop at Dundurn.
There's no plans right now to go uh past
Dund towards Westdale at the moment. Is
that correct?
>> Uh through the chair. Yes, that's
correct. And thank you. That's a that's
a really good question. um as as part of
the LRT project uh there will be some
work uh done around the 403 interchanges
and we're waiting for that to happen
before we extend the two-way conversion
further. So technically it's at the the
resurfacing is going to the CPKC bridge
uh just on the west side of Dunduran and
the the two-way will stop at Durn.
>> Okay. And for you have a few more
questions. Um, while you're doing all
the uh conversion on Main Street, will
there will there always be access to
Lock Street for people to turn in?
>> Yes, there may be restricted access on
lock. So isolated incidents where we may
need to close off a section of lock uh
in order to run the new traffic signal
ducts across, but it'll only be isolated
times. It won't be, you know, a full
closure for weeks at a time. It would
more than likely be like a half a day at
a time.
>> Okay. Thank you. Um and that won't go
much further. It'll operate just a
little like a block or so at most.
I'm sorry. Could you
>> like when when sorry when you're uh
doing things like the traffic signals at
Main and Lock, you won't be going really
far down lock. That's just in the
immediate. Okay.
>> Just in the immediate intersection.
>> Okay. Thanks. And you share a few more
questions. Brian, you mentioned that we
had specific questions about some things
like no left turn and so on. So the
summit lock, we we weren't given the
opportunity to have input. So when you
say you'll meet to discuss, is that just
to explain, not really to try to change
it?
>> Um,
in in terms of Lock Street, Shane can
correct me if I'm wrong. All all
movements will be provided at signalized
intersections. I'd have to confirm that.
But
>> yeah, but if there's um I never thought
about Lock Lock Street in terms of
getting, you know, um into that level of
detail, but but uh we would be more than
welcome to meet with Lock Street to get
your input on all things happening on
Main Street. because I thought I saw no
left side, low left turn, but I just
want to make sure that people can turn
into log left or right either direction
off off me. That's mostly my concern
>> through the chair. We'll we will reach
out to you and we'll go through the the
plan with you.
>> Perfect. Thank you so much. I appreciate
that. Thank you.
>> Thank you, Tracy. Emily, go ahead.
>> Yes. Sorry, I was just reminded uh
through your comments about uh
opportunity that we saw and throughout
this whole process uh we've kind of
thought of uh this project as an
opportunity to add some uh art along
that section whether it's crosswalk
paintings or pole roughs or whatever
like that. And uh we've kind of always
been told that we are not at that point
in the process yet. Do you know when the
point in the process to discuss adding
those kinds of things would be?
Um, we can we can discuss that in in our
one-on-one meeting. Um, the project at
at the moment doesn't include things
like pole wraps. Um, but we'll we can um
look at the proposals and and see if
things can be incorporated.
>> Okay. Thank you.
>> Go ahead, Adrian.
>> Sorry.
Um
to carry on on Tracy's question about
Dundurn, just as a Hamiltonian who lives
in the West End, just so we're clear,
you know, five lanes come off the
highway at Dundurn there and then it's
going to have to get chopped down to
two-lane traffic there, right? So just
to anticipate a headache for a bit there
until it's resolved. Uh no be uh it'll
be very similar to the way it's been
operating from 2022 up until the time
the water main lining project started.
Uh where it will the the five lanes will
feed into into three lanes. So generally
the the left turn a lot will turn left
onto Dundurn. A lot of people turn
right. So we we've been operating with
the three-lane configuration for for
three four years now.
Will there be changes? Absolutely. But
we've we've modeled it all and it and it
works.
>> Any other questions?
>> I've I've long said that I think when
people are uh doing their driver's ed
tests like coming off the highway and
then hanging a right on Dunder, if you
can do that, you're probably good to go.
Um thank you so much for your
presentation.
Sorry, Tracy, I didn't see you. Go
ahead.
>> Sorry, I stuck in when we're talking
about Dunder. That's the question. When
all this is being done, there are no
plans to have like Dunder and Aberdeen
closed when the construction's going on
on Main Street. I hope because people do
turn right to kind of get through the
neighborhoods. The locals said, "No, is
that going to happen or
>> we're we're acutely cognizant of that.
Um, and we wouldn't envision ripping up
Aberdine for the larger Aberdine project
uh until Main Street is is uh
stabilized.
>> Perfect. Hopefully the same. Nothing
undone during too. Thanks.
Okay. Um,
thank you again for your presentation.
You're welcome to stick around, but you
don't have to. Gets kind of boring from
here for you guys. So,
um, we currently do not have quorum
since it looks like Susan has stepped
out. Um, which means, uh, I can't move
her second or receive this information
until Susan returns.
So, we're just kind of in holding at the
moment.
Hopefully Susan can hear me.
So, through the chair, we will then go
into recess while we wait for Susan to
return.
>> Okay.
Please hold.
have a mover and a seconder to receive
uh the information from Brian and his
team. Moved by Emily, seconded by Steph.
Uh all in favor?
That motion is carried.
Okay, the real exciting stuff.
Uh, general information, other business
11.1 updates from the business
development office. Christina Gesler,
business development and business
improvement area officer is here with an
update for the committee. Christina,
take it away.
>> Thank you. Good morning, everybody. Um,
okay. So, um, I processed everyone's
second levy payments. Um, so hopefully
you have all received the money by now.
If you have not, please send me an
individual message. Um, and I will
follow up with that. But those were pro
those were submitted to accounts payable
some time ago. So hopefully you guys
have all seen your money. um and that
these second levy payments will take
into account reconciliations either
deficits or surpluses um based on the
taxation reports that are circulated the
end of year 2025 reports. Um in addition
all of the um grant motions those check
requis requisitions were processed as
well. I did ask accounts payable to
process them separately because they
often will lump them together and I know
sometimes it's hard to differentiate the
payment is for what. So hopefully they
did that. If you see a lump payment they
might have missed that one because they
there was a big wave of them that all
went in. Um but again if you can check
and make sure that you have received all
of the monies that you have requested
and if not just send me an individual
message and I will follow up.
Just a reminder, I know we talked about
this a little bit at the um last uh
meeting. It is an AGM election cycle.
So, um if you have not already, if you
could please let me know when your AGMs
are scheduled for. You will have to
notify your members as per the
procedural bylaw 45 days prior. Um so,
it's a bit more of an advanced notice.
Um I am working with cardioraphic
services to get the uh mailing lists and
I am still pushing and um we'll get
confirmation soon on whether or not they
can provide owner names attached to the
addresses. I had a follow-up meeting
yesterday. They're still following up
with EMPAC. I've kind I've reexplained
this is not going to an arbitrary third
party that these are actually BIA
members that there should be no
b barriers from a privacy perspective.
Um so hopefully that messaging has got
through. Um I don't have a definitive
answer as of yet but as soon as I do I
will let you all know.
>> Yesterday um or this week I don't know
what day it is. um the BA annual report
checklists. I circulated all of those um
so everyone has um the checklist of
things that are required for your annual
reports. I know that there are some
people that have had some challenges
with the sync folder. You can I don't I
don't care how I get the information.
It's just for our our um city records.
So, you can either email me if you're
having problems with the sync folder or
for those of you that have used the sync
folders without any issue, um you can
continue to use those. And there are
some BAS that have some outstanding
items from 2025. Um so, if you could
please make every effort to get those um
documents to me as soon as possible,
that would be very much appreciated.
And then finally, our RAM team, the
research and marketing team within our
economic development actually asked me
to note that um the social media
activity of all of the BAS has been
quite impressive um and has been um very
noticed. Um, and just to let you guys a
friendly reminder, if you would like to
have some amplified kind of sharing of
some of the things that are happening
within your BAS, please remember to add
um, ECD as a collaborator, so then it's
flagged because it's impossible to track
all 12 BAS. Um, but if you add um, ECD
as a collaborator on your post, then
it'll pop up on there and then there's
an opportunity for us to be able to
share all of your great stuff beyond
So that is all my updates.
>> Are there any questions for Christina?
Emily?
>> Yeah. Um, any update on the budget
templates
>> through the chair? Yes, actually I have
those done. I just [laughter] I haven't
sent them out. So, um, thank you for
actually bringing that up. So, uh, for
those that are new or kind of this is
kind of like for the AGM or for your AGM
cycles, yes, you should be preparing
your budgets in advance of your AGMs and
those really should be approved by your
boards in advance. Um, I will be
circulating, thank you for the reminder,
um, the, um, the AGM temp the budget
templates. Just a note, those templates
will only be used for the reports going
to council. I do very much encourage um
and suggest that you do have a more
detailed breakdown of your budget for
your members. Um you will see that um
the the template has just more general
categories. Um what we're aiming to do
is have a more consistent presentation
to council and to the public on what
your budgets look like. Um, but for the
purposes of your members, you may want
to be a little bit more granular when
you're talking about marketing and
advertising. You may want to get into
specifically what that means. For the
purposes of council, everything you'll
see it will be in general categories. I
will be sending those up before the end
of the week.
>> Perfect. Thank you.
>> Uh, Susan. And just on those templates
through the chair, um on the generalized
summary, we have to report to you
exactly as you're sending us the
template.
>> Yes, take a look at the template. If you
have any questions, please let me know.
Um hopefully it's clear. Um but uh but
yes, that is the that is the budget that
I would like to have back to me to to
attach to the reports that have to go to
council.
Okay. I just know even in our auditing
process,
the way our strategic plan is set up
doesn't always align with the buckets
the way the auditors report them. And um
so I'm just hoping that it's not a big
makework project for us to pull our
numbers out separately to match the
template that it might vary from the way
that we report based on our strategic
pillars. So just uh I'll wait and see.
>> Yeah, wait and see. Afterwards,
>> they've reviewed it. Yeah, the objective
is for your levy to be accounted for to
council.
>> Yeah,
>> but we'll I'll work with all of you if
there's any questions. Um I certain we
certainly the intention is not to make
it a make work but the but there it has
been noted that is quite inconsistent in
the in the the budgets that are being
presented to council. Um so we just want
to use this not only um to to make it
easier to read but um also to almost act
as an education tool for council for
them to understand how the budget how
the BIA budgets operate um and how your
monies are allocated. But I'll work with
all of you.
>> Thank you.
>> Any other questions?
>> Okay, I'm going to pass the chair to
Susan real quick because I have a
question. Christina, um we have spoken
around this table previously about um
expenditure requests both for shared
parking revenue and for contribution
operating budgets and the potential for
looking at a delegated authority
um in order to streamline that process.
Do you have an update on that
>> through the chair? So the existing
policies that are in place um for the
contribution to operating budget that
was approved in 2013.
It does specific it's it's very outdated
language. Um it does specifically say
that funding requests um to must go to
the BIA advisory committee for review
and approval. And then the shared
parking revenue policy that was approved
in 2010
talks about habia to give you an idea
how old it is. Um and um that a
resolution of habia approving the
expenditure request is required. So um
that those are the current policies as
they stand. Um it
>> Okay. Thank you. Um
when once we've received the update, um
I will
uh present
a motion to have those policies updated
if that's okay.
Um any other questions for Christina?
Seeing nothing, may I have a mover and a
seconder to receive Christina's update.
Moved by
Emily, seconded by Susan.
Uh, I don't believe I took the chair
back from Susan, so
it was implied, I suppose. [laughter]
Uh, all in favor?
That motion is carried.
Uh so then I will return the chair to
Susan so that I can introduce a motion
uh with regards to updating the current
policies.
We're just getting it up on the screen
here.
Do you want me to read this
>> through? So through the chair I think
I've captured what you're trying to do.
So maybe just take a quick glance and
let me know if anything needs to be
changed. And then we also just need a
seconder for the motion.
If anyone is willing, just raise your
hand.
I saw Emily out of the corner of my eye
there.
>> Yep.
So through the chair, this
>> the essence of what you're looking for.
>> Correct.
>> Perfect. Does anyone need it still up?
I don't see any hands. So I'll take it
down and then we can just go to
questions and if there are none, you can
call the vote.
>> Sure. Does anybody have any questions?
>> Sorry. Through the chair. It' be I
believe you handed the chair to
>> Right. I'll take the chair back from
Susan. [laughter] Does anybody have any
questions?
>> Sorry, you're the mover of the motion.
Yeah. So Susan will have to stick
handle.
>> Any questions about [laughter]
motion?
>> So through the chair, I see no hands
raised. So you can call the vote.
>> Yep. So um we've got a mover and a
seconder. All in favor?
>> Oh, I can't vote on the chair.
[laughter] That is carried. And I will
throw the chair back to Naen.
Thank you, Susan.
Great. Let's move on to statements by
members. Uh, does anybody have any
updates or items of interest? Um, raise
your hand and we'll
do that. Anybody?
No.
Okay. I'll just give a quick update on
BASH for those of you that weren't
there. Um, it was a fantastic time. For
those of you that did pop down, uh,
thank you so much for supporting what
we're doing. The mayor did make an
appearance. I got to go on stage and
introduce her and, um, she actually gave
a really great shout out to all the BAS,
um, for doing the work that we do to
bring community together, uh, in
particular with with events. Um, so it
was really nice to to see that
acknowledgement. Um, so I just wanted to
pass that on to everybody. Keep up the
great work from the mayor. Um,
all right, Emily.
Muted. Uh, I just wanted to highlight
our little soccer activation that we
have in Gore Park right now. We have
some cool soccer decor up and in
conjunction are running a giveaway. So,
um if you go and take a picture with the
photo backdrop in Gore Park, you're able
to get an extra 10 entries to win the
soccer themed gift pack. So, be sure to
check that out and snap a pick while
you're there.
>> Sounds great. Uh Susan,
>> anybody looking for a really good
workout? Our first Fridays of the season
is back. We're doing free uh workouts
led by our health and wellness and
fitness people and it starts tonight
with a a very strenuous workout in
Memorial Park. So if you're looking for
a free fitness, come join us.
Thanks Susan. Uh Steph.
Hey everyone. We have our thrift crawl
and movie night this Saturday. Thrift
Crawl starts around noon and our movie
night is at 9:00 p.m. and we're watching
The Goonies. So, if you're around,
please join us on Ottawa Street.
>> It's a classic movie right there. Uh
Adrian,
uh yeah, Hess Tomorrow has um our first
ever self-love crawl. Uh so, with the
rebranding of Hess, we have, you know,
over 15 womenowned businesses. About
half of those are in beauty. So,
eyelashes, nail salons, uh hairdressers,
etc. So, if you're looking to see uh
what Hess is turning into, tomorrow is
doors open for all these businesses,
letting you come in and giving free
giveaways. Also, in July, um following
some really cool stuff happening in
Toronto, Montreal, and New York. We're
having a huge flower market, so we're
trying to shut down the entire village
and have, you know, dozens and dozens of
flower vendors. So, keep your eye on
advertisements for that as well.
Sounds great. Um, just a side note plug
for Barton Villages uh, events library
for all those event organizers. Feel
free to let me know if there's stuff you
need. We got tons of it. Okay. Anybody
else?
May I have a mover and a seconder to
receive the statements from members?
Moved by Tracy, seconded by Jennifer.
All in favor?
Motion is carried. Being no further
business, the business improvement area
subcommittee is adjourned at 11:26 a.m.
Thanks everybody.
>> Take care everyone.
>> Have a good day.