← Back to summary
Full Transcript
Downtown Reimagined Infrastructure Project Updates - 23 Sep 23
Grimsby · September 26, 2026
we can get started. So, uh, good morning
everyone and welcome to the downtown
reimagined projects construction
information session. Thank you all for
joining us this morning. Um, so today a
member of the town of Grimby project
team will walk us through the latest
information including upcoming
construction activities, anticipated
traffic and parking impacts, and what
businesses and residents can expect as
work progresses. So before we get
started, just a quick note on questions.
Um we'll be opening the floor for
questions following the presentation. So
when we get to that portion of the
session, you can either raise your hand
using the Google Meet function or submit
your question in the chat. We'll go
through each question in the order that
they come in. And then we also ask that
questions remain focused on the
construction activities and impacts
being discussed today. um other updates
um updates on other aspects of downtown
reimagined will continue to be shared
through our project channels. So with
that, I'll turn it over to Martin Reed
from the Town of Grimsy project team to
get us started.
>> Thanks, Cass. Yeah, so my name is Martin
Reed. I'm the project lead on this
project, and I'm just going to walk you
through what we've done and what you can
expect moving forward.
So this map here shows you our sequence
of construction. Uh this seems to be an
everchanging document. Even as of about
20 minutes ago, I was speaking with the
contractor and things were changing. But
to date, we've installed the water man
all the way down Elm Street. So sections
one and two as well as down Main Street
East, which is three, four, and five.
They've been doing night work for the
last couple of weeks. And as of this
morning, they just wrapped up in section
five and they've crossed over into
section six.
Been pretty challenging. There's been a
lot of rock in the ground, utilities in
the ground. We dug up an existing old
trolley line, so a concrete base and all
of the wooden supports for the tracks
going all the way down Main Street. and
also have to shift our alignment a few
times due to some conflicts with
existing utilities.
We're moving to Rossmore. Um part of the
change is that we are trying to get
directional drilling going on Rossmore.
>> So, as you can see in the next slide
here, that's Rossmore Avenue, which
branches off of Main Street East.
Not too far.
There we go.
So 30 minutes ago had a conversation
with the contractor. We are going to be
proceeding with directional drilling on
Rossmore, which means that they won't
actually be digging up the road with an
excavator. They'll have a machine come
in similar to what we did when we had to
go underneath the 40 mile creek at Elm
Street where they dig a pit at one end
and a pit at the other end and they
drill the water mane in underground. So
minimal excavation
and one of the biggest benefits to
approaching it this way is that it frees
up one of our crews so that they can go
and work concurrently in another section
of the project area.
This will also minimize the restoration
impacts on Rossmore. It's pretty narrow
road in there, so I'm sure the residents
will be pleased that we're not ripping
and tearing up the road and the curb and
whatnot. So, I do anticipate that that's
going to advance the schedule fairly
significantly for us.
So, that's going to be happening
starting next week. Uh, for the next
couple of days, the crew will be coming
back on Thursday because they're
transitioning from the night shift back
into dayshifts and they're going to be
doing some cleanup and some restoration
in the areas where they've already
installed the water man. So, the rest of
the week they'll be kind of bouncing
around on Elm Street
restoring some of the cross trenches,
probably prepping some of the sidewalk
that they've removed in order to to
actually pour those sections of
sidewalk.
>> And then on Monday,
keep that slide for now. On Monday,
we're hoping to start on Main Street
West. Uh we had some issues with Bell
and their locates. They had some
unlocatable plant in the ground that
wasn't identified during the design
phase and unfortunately we've not had
[snorts] much luck for the last few
weeks getting somebody out there to
verify for us. We have some asurances
they'll be out there on Monday. Uh and
we've been shaking some trees to try and
get somebody out there this week so we
can be prepared to start for certainty
on Monday
on Main Street West.
We're going to be keeping one lane open
while we do that construction. It's
between the 40 mile creek and Patton
Street. Goes a little bit beyond Patent
Street where we're reconnected to the
existing water man. And we'll have flag
people on site to direct traffic. So it
it is going to back up traffic down Main
Street, likely impact Christian Mountain
as well, but we're not planning on doing
a full closure here. So, it will be
daytime work and we are going to be
accommodating
traffic as efficiently as we can through
there.
Sorry about that. So, following Main
Street West, we'll be moving to the
intersection of Elm Street and Mountain
Street. Similarly to what we did at the
Elm and Main Street intersection, we're
going to be doing this as a nighttime
closure because of the traffic impacts
as well as the impacts to businesses.
Uh, this one's a little bit trickier
than the Elm Street and Main Street
intersection. And that this is a major
truck route up and down the escarment.
So, the night work here is important not
only for trucks, but also for
residential and business traffic coming
through the area. Uh because it is
nighttime work, we are going to again be
stockpiling material at the Lion's Pool
parking lot because none of the soil
receiving sites are open during the
nighttime.
We're anticipating this is going to take
four or five nights to complete and
every morning we'll be reopening it to
regular traffic operations. So, the
closure will commence at 8:00 PM nightly
and then we'll reopen road by 6:00 a.m.
the following day.
>> This is just an example of the detour
plan. We've been posting these on our
website to keep people informed of how
they can navigate these closures. This
one in particular is for
cars that are trying to get up the
escarment. So, because we'll have the
intersection closed, there will be no
through traffic at that intersection.
So, anybody who needs to get up the
mountain is going to have to detour to
Park Road or alternatively, they can
head westbound and go up Wolverton.
Truck traffic's a little more complex
because neither Wolverton nor park can
accommodate heavy trucks. So, we're
actually setting up detours. They're out
there today on the highway setting up an
advanced notification sign to notify
truck drivers that they're going to have
to either go up the Red Hill Valley
Parkway in Stone Creek or go to Victoria
Avenue in Binland in order to get up the
mountain.
>> We're looking at notifying the various
uh navigational companies, Google Maps,
Ways, seeing if they can put advanced
notice on there. Although I do know that
once it is closed, they have real time
updates that will inform people that
they're not going to be able to use
Mountain Road as an access.
This is relevant for the nighttime
closure, but also for the next stage,
which will be a full closure of Mountain
Street between Elm and Main Street.
So, in this section, we're not only
replacing the water man, we're also
doing sanitary sewer work, abandoning
one sanitary main because there's
currently two sanitary mains running
down the street. So, we're abandoning
one of the mains and then transferring
the services over to the other main. So,
the water man going in at the center
line of the road means we weren't able
to keep it open to truck traffic safely.
and all of the crossings as well because
we're having sanitary services as well
as water services means that there's
just too much open cutting happening
within this road to safely keep it open.
It will mean that we're going to have to
close the entrance to the food basics
parking lot that comes in off of
Mountain Street there as well as the
entrance to the Balsson Lane municipal
parking lot.
Now, although those two entrances will
be closed, we do have to still maintain
access for the residents who live on
that street. Uh there's also a funeral
home there. So, we're going to be
navigating access with all of those
individual properties and we'll be
setting up a meeting in advance of this
work just to assess their needs in terms
of timing and frequency of access. I
know there's also a church there that's
currently under construction and I've
been in contact with uh one of the
members of the church with respect to
that and we'll have to accommodate their
construction vehicles as best we can.
This work is going to be a longer
duration. Um I know that the soil
conditions here are pretty rough after
having going gone down Elm and seeing
the amount of rock in the ground and the
massive fertilities going through there.
So, we're anticipating this full closure
of Mountain Road will take somewhere in
the realm of four weeks.
This is an example of the local detour
for cars that have to navigate around.
Fortunately, we'll have Elm Street and
Main Street open, so it'll be fairly
easy to navigate through there. We also
have two access to that food basics
parking lot. One off of Main Street and
one off of Elm Street. And Falsam Lane
also has an entrance off of Elm. So,
we're hoping this won't be too much of a
convenient for the businesses and the
residents, but we really didn't have an
option here in terms of the full closure
based on the scope of work.
And this similarly to the example I
showed for the intersection at Elman
Mountain. This is just showing the truck
detour route.
Once we finish that section between
Maine and Elm Street, then we have to do
the other major intersection which is
the Christy Mountain and Main Street
intersection.
So there again, due to the location of
our water man and the amount of work
through here, we have to close the
intersection in order to get it done
quickly and safely. So, this will be
another nighttime closure, and we
anticipate this one's going to take five
days, so an entire work week to
complete, reopening it during daytime
hours. So, this is this is probably the
the busiest intersection in town. So, to
try and do the work and manage cars just
wasn't going to be practical, and it
would have dragged the work out to two
to three times as long. So given the
success of the Elm Street works at
night, we're also going to be doing this
as a nighttime closure because it
minimizes the impacts on [snorts]
residents and the businesses.
And I'm not sure if trucks drive more at
night or during the day, but my hope is
that it'll also minimize impacts on them
as well, given that we'll have had
Mountain Street closed for approximately
four weeks before this.
Another
example of the detour for local traffic.
Cars can get around via Elm Street. Um,
locals also know they can go down
Ontario Street. And there's there's a
few different ways they can navigate
through, but this is where we're
recommending is that they go down to
Bells and then use Clark Street to get
around this closure.
It's the truck detour again. And then
our final section that we have to
complete will be the remaining length of
Christy Street up to the entrance to the
municipal parking lot there. So
Elizabeth Street dead ends here in a
little grass area. So our water man is
going to be reconnected between the
curved line for the parking lot entrance
and that dead end stub for Elizabeth
Street. We'll be coming up the
east side of the road and we're hoping
to keep two lanes open through here to
keep through traffic in both directions.
But if we do that, we're going to have
to restrict the left turn movements off
Christy Street onto Maine just to keep
things moving because if you have cars
queuing up to turn left, it's going to
really gum up the works there. So,
anybody looking to go onto Main Street,
they'll be able to just carry on to Elm
and then turn left onto Elm Street.
The last step in this whole process, and
I'm hoping this will be completed in in
more than just one section, is the
commissioning process. So, the final
testing of the water manes, we need to
swab them
pressurize them to make sure it's not
leaking and then we chlorinate to
disinfect them and then bacteria test
them. So that whole process
is to make sure that the water mane is
clean and that it's free of leaks so
that we can then reconnect it to the
existing system. The reconnections
themselves will involve digging up the
ends of all the sections of pipe that we
have currently installed. So at at this
time any pipe that we've installed is
not in service. It's just empty pipe
sitting in the ground. And then once
we've gone through the commissioning
process, we dig up those ends and cut
into the existing water mane to make our
final connections. So the main line is
connected and then following the
connection of the mainline water man to
the existing system. Then we do all the
individual services. So at each property
line, we'll have to excavate at the
property line and then disconnect each
home or business from their existing
service and connect it to the newly
installed service. So this will this
will mean some more disruption to each
property. Uh although we say we're done
installing water main section, that is
true in terms of the main line and the
larger disruption of us coming down the
street. So once we're ready to do final
connections, it'll be a large number of
individual excavations that we're doing
to make sure we can connect it to the
existing system.
That's the end of my slideshow, but I'm
going to go back here because we had
some developments here just with respect
to paving about 20 minutes ago. Uh we've
been tenatively scheduled to start
Monday. The contractor is now proposing
the idea of doing around the clock
paving. So that would mean they have two
separate crews working around the clock
24 hours in order to get all of the
areas that we've currently installed the
water mane restored with asphalt up to
the surface. So it's been pretty pretty
rocky and pretty dusty. Uh there have
been some concerns. a few insurance
claims for damaged rims. Doing our best
to keep the trenches in in good working
order and drivable condition, but it is
challenging when especially on Main
Street. We had to take up half of the
road in order to remove that old rail
line. So, the intent is to get in here
early next week or even possibly Sunday
night in order to start doing the
permanent pavement restoration. So that
would clean up Elm Street and Main
Street, the areas that we've completed
thus far. There is still some internal
discussions that need to happen with
respect to this given that it just came
up about 20 minutes ago. But it will be
good to have these areas permanently
restored and then at least for now all
of those areas that we've open cut will
be finished until we have to go back in
and do all of the final water main
connections.
For any business owners that are on
Mountain Street,
uh, one thing I wanted to add is that we
will be keeping the sidewalk open. So,
the majority of the work is happening
within the roadway in terms of the water
man itself, but when we go to do all of
the individual service connections, we
will be cutting across the sidewalk. So
that's going to make things a little bit
tricky for access. There will always be
access from either the north side or the
south side, but that's going to change
daily based on what services we're
installing at that time. So that's going
to be something where there's daily
coordination as well as wayfinding
signage that's put in place just to make
sure people know how they can navigate
to the businesses that they're trying to
reach on there. There are less
businesses on this section than there
are on Main Street, but we we are aware
that especially on the east side of the
street here, you have a row of
businesses as well as that uh funeral
home which is going to have very
specific needs for access. So, we will
send out more communications when we get
closer to the point of working there on
Mountain Street, but for now, just know
that uh there will be a lot of
communication happening, and we'll make
every effort to make sure that every
business and every home on that section
is accessible at all times. They just
may have to change up how they're
accessing that business depending on
what we're what we're digging at that
time.
And that's all I have for the
presentation. Just taking a quick look
at my notes here to see if I missed
anything.
But Cass, if you want to open it up to
questions, take any questions that
people might have.
>> Thanks, Martin. Um, thank you for the
presentation and for walking us through
those updates. We'll now open the floor
for questions. You can either raise your
hand, go off mute, or pop put your
question in the chat, and then we'll
work through the those questions in the
order that they come in.
I will add one thing just quickly in
regards to the night work. Um if you
you're probably aware or have heard
about it, but we were stockpiling
material from the network at the Lion's
Pool.
Um we did change up the way that we were
doing that work because we had some
complaints about the noise. So rather
than consolidating material throughout
the night, we ended up just dumping
dumping out of the trucks onto the
parking lot and then cleaning it up the
next day. We're trying to minimize the
amount of noise at night and one of the
concerns that's been brought up is if we
do have these paving operations running
through the night, that is a pretty
noisy operation. So within our
discussions about how we're going to
execute the paving, my hope is that we
can do Elm Street during the day and
focus more on the high traffic areas in
the area where we did more of the
pavement removal on Main Street at
night. So, we do apologize for the
inconvenience of the nighttime noise,
but it has been very helpful to the
businesses and to people's daily
routines, but it is unfortunately
disproportionately disruptive to those
people who live in the area. So, we're
trying to be mindful of that and
mitigate it as much as possible while
also expediting the project as as
quickly as we can.
>> That's good, Martin. Thank you. Um, are
there any questions?
>> So, Cass, we did see one pop up in the
uh
>> chat.
>> Uh, just a question was when do we
expect the construction end in 2026?
>> So, we're targeting the beginning of
December. Uh, we're trying to push this
schedule so all the installation is done
by the end of November. the restoration
work, particularly sod and the final
restoration of all the individual
properties that will likely stretch
either further into winter or obviously
due to the availability of sod it may
have to be deferred until early 2027.
Uh, I will say that as long as we can
get sod,
putting it down, even right up until
December, it actually takes better than
sod that is planted in,
>> you know, mid to late spring or even
early summer. It ends up going dormant
and then with all of the snow and the
thaw that comes in over the winter, it
it really does quite well in the spring.
So ideally we want to try and get as
much of this done as possible before
December, but obviously we have quite a
bit of work left to do. So we're just
trying to advance the schedule wherever
we can. And that's where this idea of
doing the directional drilling on
Rossmore came up and it's something that
we're we're working to execute in order
to expedite the construction process.
Thanks, Martin.
So, if there are no other questions, um
we would want to thank everyone for
joining us this morning. Um we know
there's a lot of information to take in
as construction progresses and we
appreciate everyone taking the time to
join us and stay informed. Um so, we'll
be sharing a recording following today's
session. Um, we also encourage everyone
to stay uptodate on the project by
visiting let's
talkgrimsby.ca/dr--construction.
Um, you can select follow project to
receive updates directly in your inbox.
Also, please follow our Facebook and
Instagram channels at downtown
reimagined for ongoing project updates
and information. Um, if you have any
questions following this session, you
can also reach the downtown reimagined
team at dt re-imagined atgsby.ca.
That's dt re-imaginedgrimsby.ca.
Um, so thank you again everyone for
joining us this morning. Um, we'll give
you some time back and hope you have a
great rest of your day and week.